RFA Fort Victoria Bridge Refit
Wide-ranging work was carried out to ensure full compatibility with the International Maritime Organisation (IMO) MARPOL regulations. Improvements to the Replenishment at Sea (RAS) equipment will now enable the vessel to replenish the new Queen Elizabeth Aircraft Carriers. Meanwhile, an upgrade to the Bridge section will ensure a modern approach to naval navigation.
SeaKing Group Managing Director Dave Gillam said the firm was initially tasked by Cammell Laird and the MoD to provide a feasibility study which would later form the basis of the Bridge design.
“After carrying out a full inspection of the Bridge area we submitted a series of options to the MoD ranging from minimal work to a complete overhaul of the layout with significant changes to the ship structure,” he said. “The decision was then made to strip the entire interior of the Bridge back to its shell and replace it with a more efficient layout.
“The new design was based around previous installations on RFA vessels which SeaKing had delivered in close partnership with Cammell Laird. It involved the installation of four separate consoles. SeaKing was responsible for the overhaul and reconfiguration of legacy equipment and the installation of new equipment. This included the new RADAR’s, Warship Electronic Charting Display & Information System (WECDIS) and the Navigation Distribution & Conning System (NDACS).”
Alongside other nominated sub-contractors, SeaKing was also tasked with full system integration within the Bridge section. This included the set up and synchronisation of key equipment such as steering gear, signals and controls, wind speed and direction, gyro inputs, ships speed log, pitch and roll, ships AIS, voyage data recordings, main engine and propulsion signals, new NVG compatible navigation lighting and associated controls, and numerous other naval communications systems.
Additional work involved the design, manufacture and installation of a new deck lighting control system. This was achieved with an HMI Touchscreen providing automated control.
On completion of the project SeaKing received commendations from both RFA Superintendents and OEM Directors on the level of diligence, workmanship and effort to complete a specification which was not fully developed at the outset.
Enquiry Form
From breakdowns to major refits, if you have a project you would like us to quote for, please get in touch using the form below and one of our team will be in touch shortly to discuss you exact requirements.